Novarly ParcelRenewable sites

Renewable sitesLanghope Rig

Langhope Rig

Langhope Rig is an operational 16 MW onshore wind farm in Scottish Borders, generating since 26 March 2015. Planning permission was granted on 17 July 2007, 13 months after submission. Operator of record: Greencoat UK Wind.

16 MW
Capacity
as recorded in REPD
Operational
Status
since 26 March 2015
Wind Onshore
Technology
Greencoat UK Wind
Scottish Borders
Authority
Scotland

Planning and build timeline

Application submitted30 June 2006
Permission granted17 July 2007
13 months after submission
Operational26 March 2015
92 months after consent

Screening a site of your own?

RedlineUK · £39

Scottish Borders approves 56% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Langhope Rig’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Borders’s record on onshore wind

Scottish Borders has decided 41 onshore wind schemes and approved 56%, taking a median of 13.6 months. See every onshore wind scheme decision in Scottish Borders

How big is Langhope Rig?

Langhope Rig has a recorded installed capacity of 16 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Langhope Rig?

REPD records the operator as Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Langhope Rig approved and built?

The application was submitted on 30 June 2006. Permission was granted on 17 July 2007, 13 months later. The site became operational on 26 March 2015, 92 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4620.

Novarly Parcel · official public data, read properly · parcel.novarly.com