Renewable sites › Langhope Rig
Langhope Rig
Langhope Rig is operational in Scottish Borders with a recorded capacity of 16 MW, and has been generating since 2015-03-26.
Planning and build timeline
| Application submitted | 2006-06-30 |
| Permission granted | 2007-07-17 13 months after submission |
| Operational | 2015-03-26 92 months after consent |
Scottish Borders’s record on onshore wind
Scottish Borders has decided 41 onshore wind schemes and approved 56%, taking a median of 13.6 months. See every onshore wind scheme decision in Scottish Borders →
How big is Langhope Rig?
Langhope Rig has a recorded installed capacity of 16 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Langhope Rig?
REPD records the operator as Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Langhope Rig approved and built?
The application was submitted on 2006-06-30. Permission was granted on 2007-07-17, 13 months later. The site became operational on 2015-03-26, 92 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4620.