Land at Morfa Camp

Land at Morfa Camp is an operational 2.8 MW solar farm in Gwynedd, generating since 20 March 2016. Planning permission was granted on 19 October 2015, 4 months after submission. Operator of record: Novus Solar Developments.

2.8 MW
Capacity
as recorded in REPD
Operational
Status
since 20 March 2016
Solar Photovoltaics
Technology
Novus Solar Developments
Gwynedd
Authority
Wales

Planning and build timeline

Application submitted1 July 2015
Permission granted19 October 2015
4 months after submission
Operational20 March 2016
5 months after consent

Screening a site of your own?

RedlineUK · £39

Gwynedd approves 82% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land at Morfa Camp’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Gwynedd’s record on solar

Gwynedd has decided 11 solar farms and approved 82%, taking a median of 3.6 months. See every solar farm decision in Gwynedd

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
3.99.4 km

How big is Land at Morfa Camp?

Land at Morfa Camp has a recorded installed capacity of 2.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land at Morfa Camp?

REPD records the operator as Novus Solar Developments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land at Morfa Camp approved and built?

The application was submitted on 1 July 2015. Permission was granted on 19 October 2015, 4 months later. The site became operational on 20 March 2016, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5389.