Land at Morfa Camp
Land at Morfa Camp is operational in Gwynedd with a recorded capacity of 2.8 MW, and has been generating since 2016-03-20.
Planning and build timeline
| Application submitted | 2015-07-01 |
| Permission granted | 2015-10-19 4 months after submission |
| Operational | 2016-03-20 5 months after consent |
Gwynedd’s record on solar
Gwynedd has decided 11 solar farms and approved 82%, taking a median of 3.6 months. See every solar farm decision in Gwynedd →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Braich Ddu Wind Onshore · Operational | 3.9 | 9.4 km |
How big is Land at Morfa Camp?
Land at Morfa Camp has a recorded installed capacity of 2.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land at Morfa Camp?
REPD records the operator as Novus Solar Developments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land at Morfa Camp approved and built?
The application was submitted on 2015-07-01. Permission was granted on 2015-10-19, 4 months later. The site became operational on 2016-03-20, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5389.