Novarly ParcelRenewable sites

Renewable sitesBraich Ddu

Braich Ddu

Braich Ddu is operational in Gwynedd with a recorded capacity of 3.9 MW, and has been generating since 2007-08-31.

3.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2007-08-31
Wind Onshore
Technology
REG Windpower (previously Cornwall Light and Power)
Gwynedd
Authority
Wales

Planning and build timeline

Application submitted2004-03-11
Permission granted2004-09-13
6 months after submission
Operational2007-08-31
36 months after consent

Other built sites within 15 km

SiteMWDistance
Land at Morfa Camp
Solar Photovoltaics · Operational
2.89.4 km
Mynydd Gorddu Wind Farm
Wind Onshore · Operational
10.214.4 km

How big is Braich Ddu?

Braich Ddu has a recorded installed capacity of 3.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Braich Ddu?

REPD records the operator as REG Windpower (previously Cornwall Light and Power). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Braich Ddu approved and built?

The application was submitted on 2004-03-11. Permission was granted on 2004-09-13, 6 months later. The site became operational on 2007-08-31, 36 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4022.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council