Renewable sites › Heathfield 'C' Landfill Scheme
Heathfield 'C' Landfill Scheme
Heathfield 'C' Landfill Scheme is an operational 2.2 MW landfill gas site in Teignbridge, generating since 4 August 1998. Planning permission was granted on 14 July 1997, 4 months after submission. Operator of record: Haul Waste Limited.
Planning and build timeline
| Application submitted | 20 March 1997 |
| Permission granted | 14 July 1997 4 months after submission |
| Operational | 4 August 1998 13 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Teignbridge: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Heathfield 'C' Landfill Scheme’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 6.5 | 5.7 km |
Solar Photovoltaics · Operational | 12 | 7.7 km |
Solar Photovoltaics · Operational | 6.5 | 12.6 km |
Landfill Gas · Operational | 2 | 14.3 km |
How big is Heathfield 'C' Landfill Scheme?
Heathfield 'C' Landfill Scheme has a recorded installed capacity of 2.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Heathfield 'C' Landfill Scheme?
REPD records the operator as Haul Waste Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Heathfield 'C' Landfill Scheme approved and built?
The application was submitted on 20 March 1997. Permission was granted on 14 July 1997, 4 months later. The site became operational on 4 August 1998, 13 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 740.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode