Gallowhill

Gallowhill is an operational 1.8 MW onshore wind farm in Orkney Islands, generating since 18 February 2013. Planning permission was granted on 2 March 2009, 5 months after submission. Operator of record: Private Developer.

1.8 MW
Capacity
as recorded in REPD
Operational
Status
since 18 February 2013
Wind Onshore
Technology
Private Developer
Orkney Islands
Authority
Scotland

Planning and build timeline

Application submitted13 October 2008
Permission granted2 March 2009
5 months after submission
Operational18 February 2013
48 months after consent

Screening a site of your own?

RedlineUK · £39

Orkney Islands approves 93% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Gallowhill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Orkney Islands’s record on onshore wind

Orkney Islands has decided 28 onshore wind schemes and approved 93%, taking a median of 6.2 months. See every onshore wind scheme decision in Orkney Islands

How big is Gallowhill?

Gallowhill has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Gallowhill?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Gallowhill approved and built?

The application was submitted on 13 October 2008. Permission was granted on 2 March 2009, 5 months later. The site became operational on 18 February 2013, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3693.