Felinfach is operational in Ceredigion with a recorded capacity of 3.2 MW, and has been generating since 2016-03-15.
Planning and build timeline
| Application submitted | 2014-01-22 |
| Permission granted | 2014-05-29 4 months after submission |
| Operational | 2016-03-15 22 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Nanthenfoel Farms Solar Photovoltaics · Operational | 5 | 5.6 km |
How big is Felinfach?
Felinfach has a recorded installed capacity of 3.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Felinfach?
REPD records the operator as Volac. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Felinfach approved and built?
The application was submitted on 2014-01-22. Permission was granted on 2014-05-29, 4 months later. The site became operational on 2016-03-15, 22 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6016.
Novarly Parcel · official public data, read properly · parcel.novarly.com