Novarly ParcelRenewable sites

Renewable sitesEast Anglia 1 (EA 1)

East Anglia 1 (EA 1)

East Anglia 1 (EA 1) is an operational 714 MW offshore wind farm in England, generating since 28 July 2020. Planning permission was granted on 17 June 2014, 19 months after submission. Operator of record: Scottish Power Renewables.

714 MW
Capacity
as recorded in REPD
Operational
Status
since 28 July 2020
Wind Offshore
Technology
Scottish Power Renewables
National
Authority
England

Planning and build timeline

Application submitted21 November 2012
Permission granted17 June 2014
19 months after submission
Operational28 July 2020
73 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with East Anglia 1 (EA 1)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Wind Offshore · Under Construction
14000 km

How big is East Anglia 1 (EA 1)?

East Anglia 1 (EA 1) has a recorded installed capacity of 714 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates East Anglia 1 (EA 1)?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was East Anglia 1 (EA 1) approved and built?

The application was submitted on 21 November 2012. Permission was granted on 17 June 2014, 19 months later. The site became operational on 28 July 2020, 73 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2524.

Novarly Parcel · official public data, read properly · parcel.novarly.com