Renewable sitesDonich Water Hydro

Donich Water Hydro

Donich Water Hydro is an operational 1.4 MW hydro scheme in Argyll and Bute, generating since 8 September 2016. Planning permission was granted on 12 September 2014, 16 months after submission. Operator of record: Gilkes Energy/Broadland Energy.

1.4 MW
Capacity
as recorded in REPD
Operational
Status
since 8 September 2016
Small Hydro
Technology
Gilkes Energy/Broadland Energy
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submitted28 May 2013
Permission granted12 September 2014
16 months after submission
Operational8 September 2016
24 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Argyll and Bute: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Donich Water Hydro’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
1513.5 km
Small Hydro · Operational
113.9 km

How big is Donich Water Hydro?

Donich Water Hydro has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Donich Water Hydro?

REPD records the operator as Gilkes Energy/Broadland Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Donich Water Hydro approved and built?

The application was submitted on 28 May 2013. Permission was granted on 12 September 2014, 16 months later. The site became operational on 8 September 2016, 24 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 450.