Novarly ParcelRenewable sites

Renewable sitesDonich Water Hydro

Donich Water Hydro

Donich Water Hydro is operational in Argyll and Bute with a recorded capacity of 1.4 MW, and has been generating since 2016-09-08.

1.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-09-08
Small Hydro
Technology
Gilkes Energy/Broadland Energy
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submitted2013-05-28
Permission granted2014-09-12
16 months after submission
Operational2016-09-08
24 months after consent

Other built sites within 15 km

SiteMWDistance
Clachan Flats Wind Farm
Wind Onshore · Operational
1513.5 km
Glen Fyne 'Merk' Hydro
Small Hydro · Operational
113.9 km

How big is Donich Water Hydro?

Donich Water Hydro has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Donich Water Hydro?

REPD records the operator as Gilkes Energy/Broadland Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Donich Water Hydro approved and built?

The application was submitted on 2013-05-28. Permission was granted on 2014-09-12, 16 months later. The site became operational on 2016-09-08, 24 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 450.

Novarly Parcel · official public data, read properly · parcel.novarly.com