Renewable sites › Cleveland Potash
Cleveland Potash
Cleveland Potash is an operational 6 MW battery storage site in Redcar and Cleveland, generating since 1 October 2017. Planning permission was granted on 2 March 2016, 2 months after submission. Operator of record: Kiwi Power.
Planning and build timeline
| Application submitted | 7 January 2016 |
| Permission granted | 2 March 2016 2 months after submission |
| Operational | 1 October 2017 19 months after consent |
Screening a site of your own?
Redcar and Cleveland approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Cleveland Potash’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- National Park — North York Moors
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Redcar and Cleveland’s record on battery storage
Redcar and Cleveland has decided 5 battery storage schemes and approved 100%, taking a median of 1.8 months. See every battery storage scheme decision in Redcar and Cleveland →
How big is Cleveland Potash?
Cleveland Potash has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Cleveland Potash?
REPD records the operator as Kiwi Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Cleveland Potash approved and built?
The application was submitted on 7 January 2016. Permission was granted on 2 March 2016, 2 months later. The site became operational on 1 October 2017, 19 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6892.