Renewable sites › Callagheen
Callagheen
Callagheen is operational in Fermanagh and Omagh with a recorded capacity of 22.8 MW, and has been generating since 2005-12-01.
Planning and build timeline
| Application submitted | 2001-12-27 |
| Permission granted | 2004-04-08 27 months after submission |
| Operational | 2005-12-01 20 months after consent |
Fermanagh and Omagh’s record on onshore wind
Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92%, taking a median of 20.9 months. See every onshore wind scheme decision in Fermanagh and Omagh →
How big is Callagheen?
Callagheen has a recorded installed capacity of 22.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Callagheen?
REPD records the operator as B9 / Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Callagheen approved and built?
The application was submitted on 2001-12-27. Permission was granted on 2004-04-08, 27 months later. The site became operational on 2005-12-01, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4673.