Ben Aketil is an operational 23 MW onshore wind farm in Highland, generating since 1 September 2007. Planning permission was granted on 5 September 2005, 36 months after submission. Operator of record: RDC Scotland (Renewable Development Co.).
Planning and build timeline
| Application submitted | 30 August 2002 |
| Permission granted | 5 September 2005 36 months after submission |
| Operational | 1 September 2007 24 months after consent |
Screening a site of your own?
Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Ben Aketil’s recorded coordinate — swap in your own postcode or coordinates.
Highland’s record on onshore wind
Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 4.6 | 0 km |
Wind Onshore · Operational | 41.4 | 4.7 km |
How big is Ben Aketil?
Ben Aketil has a recorded installed capacity of 23 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ben Aketil?
REPD records the operator as RDC Scotland (Renewable Development Co.). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ben Aketil approved and built?
The application was submitted on 30 August 2002. Permission was granted on 5 September 2005, 36 months later. The site became operational on 1 September 2007, 24 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3135.