Novarly ParcelRenewable sites

Renewable sitesAllt Eilidh

Allt Eilidh

Allt Eilidh is under construction in Highland with a recorded capacity of 0.6 MW.

0.6 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Small Hydro
Technology
Glen Creran Hydro
Highland
Authority
Scotland

Planning and build timeline

Application submitted2018-12-18
Permission granted2019-08-16
8 months after submission
Operationalnot recorded

Other built sites within 15 km

SiteMWDistance
Duror 2 Hydro Scheme
Small Hydro · Under Construction
0.46.4 km
Glen Etive Estate Phase I (Allt na Chaorainn)
Small Hydro · Under Construction
1.413.1 km

How big is Allt Eilidh?

Allt Eilidh has a recorded installed capacity of 0.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Allt Eilidh?

REPD records the operator as Glen Creran Hydro. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Allt Eilidh approved and built?

The application was submitted on 2018-12-18. Permission was granted on 2019-08-16, 8 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7318.