Battery storage planning in Tendring
Tendring has decided 3 battery storage schemes and approved 67% of them, taking a median of 9.4 months to decide. Consented capacity: 50 MW. 1 application still awaiting a decision.
⚠️ Small caseload (3 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Tendring compares
Against the 137 UK authorities with 5+ battery storage decisions, Tendring sits in the 4th percentile for approval rate (25 points below the England average) and the 15th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (4)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Waste Transfer Station, Ardleigh - Battery Energy Storage AMP Clean Energy · 25/00737/FUL · 3.7 mo to decide | 0.2 | Awaiting Construction | 2025-09-05 |
Land North of Horsley Cross - Solar Farm & Battery Energy Storage Mespil Solar Energy · 25/01056/FUL | — | Application Submitted | 2025-07-29 |
Halstead Road Eco Hub - Solar Farm & Battery Storage Naturalis Energy Developments Limited · 21/02181/FUL · 10.5 mo to decide | 3 | Application Refused | 2022-11-28 |
Ardleigh Road, Little Bromley - Battery Energy Storage Lawford Power Limited · 21/02070/FUL · 9.4 mo to decide | 50 | Awaiting Construction | 2022-09-28 |
Does Tendring approve battery storage schemes?
Yes — of the 3 battery storage schemes Tendring has decided, 67% were approved (2 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Tendring?
The median time from application to decision is 9.4 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Tendring consented?
50 MW has been consented across 2 approved schemes, with 3 MW refused. A further 1 application awaits a decision.
Other technologies in Tendring
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.