Solar planning in Tameside

Tameside has decided 8 solar farms and approved 100% of them, taking a median of 1.8 months to decide. Consented capacity: 7 MW. 1 application still awaiting a decision.

100%
Approved
8 granted · 0 refused
1.8 mo
Median decision
UK 2.3 mo
7 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Tameside compares

Against the 298 UK authorities with 5+ solar decisions, Tameside sits in the 77th percentile for approval rate (7 points above the England average) and the 74th percentile for speed.

Decisions by year

35Approved — 1 (2023)123Approved — 3 (2024)324Approved — 3 (2025)325
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (9)

SchemeMWStatusDecided
Morrisons Superstore, Mottram Road - Solar Panels
Sigma Group · 25/00816/NPV · 1.6 mo to decide
0.48Awaiting Construction2025-11-18
Laurus Ryecroft High School, Lumb Lane - Solar Panels
Located Property Limited · 25/00617/NPV · 1.8 mo to decide
0.27Awaiting Construction2025-09-18
Tameside College, Beaufort Road - Solar Panels
Tameside College · 25/00616/NPV · 1.8 mo to decide
0.4Awaiting Construction2025-09-17
Morrisons Superstore, Saxon Street - Solar panels
Gondola Pro · 24/00272/NPV · 1.7 mo to decide
0.46Awaiting Construction2024-05-17
Burlington Street - Solar PV Panels
Whitecroft Lighting Limited · 23/01038/NPV · 1.8 mo to decide
0.91Awaiting Construction2024-01-18
Concordia - Solar Panels
Powell Concordia · 23/01018/NPV · 1.8 mo to decide
0.24Awaiting Construction2024-01-09
Denton Hall Farm Road, Denton - Solar Photovoltaic System
System 3 Limited · 21/01436/FUL · 18 mo to decide
1.16Operational2023-07-13
Burlington Street - Solar PV Panels
Whitecroft Lighting Limited · 21/01420/NPV
1Revised2021-12-07
Godley Water Treatment Works
United Utilities
3Operational

Does Tameside approve solar farms?

Yes — of the 8 solar farms Tameside has decided, 100% were approved (8 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Tameside?

The median time from application to decision is 1.8 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Tameside consented?

7 MW has been consented across 8 approved schemes. A further 1 application awaits a decision.

Other technologies in Tameside

Battery storage in TamesideOnshore wind in Tameside

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com