Novarly ParcelRenewable planning

Renewable planning SolarMid Suffolk

Solar planning in Mid Suffolk

Mid Suffolk has decided 17 solar farms and approved 88% of them, taking a median of 5.7 months to decide. Consented capacity: 246 MW. 4 applications still awaiting a decision.

88%
Approved
15 granted · 2 refused
5.7 mo
Median decision
UK 2.3 mo
246 MW
Consented
1 MW refused
1
Appeals
1 allowed on appeal

How Mid Suffolk compares

Against the 298 UK authorities with 5+ solar decisions, Mid Suffolk sits in the 21st percentile for approval rate (5 points below the England average) and the 4th percentile for speed.

Decisions by year

510Approved — 3 (2021)321Approved — 3 (2023)Refused — 1 (2023)423Approved — 5 (2024)Refused — 1 (2024)624Approved — 2 (2025)225Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (23)

SchemeMWStatusDecided
Valley Farm, Hessett - Solar Panels
Opdenergy UK Limted · DC/25/02730 · 9.2 mo to decide
42Awaiting Construction2026-03-23
Home Farm - Solar Panels
Cranswick Plc · DC/26/01046
0.32Application Submitted2026-03-12
Blacksmiths Lane, Middlewood Green - Solar Farm
Low Carbon Limited · DC/23/04644 · 21.9 mo to decide
30Awaiting Construction2025-08-08
Bury Road, Wortham - Solar Farm
Regener8 Power Limited · DC/25/03257
Application Submitted2025-07-22
Burnt House Farm, Hoxne Road - Solar PV Array
Ford Farms (Suffolk) Limited · DC/24/03003 · 5.2 mo to decide
0.3Awaiting Construction2025-01-03
Gressingham Foods, Hinderclay Road - Solar Array
Centrica Business Solutions UK Ltd · DC/24/02233 · 5.7 mo to decide
3.53Awaiting Construction2024-11-11
Brick Kiln Farm, Sandy Hill - Solar Array
Retreat East Limited · DC/23/04182 · 3.5 mo to decide
Application Refused2024-06-07
Climax Molybdenum UK Limited, Needham Road - Solar PV Panels
Climax Molybdenum UK Ltd · DC/23/04966 · 6 mo to decide
1.2Awaiting Construction2024-05-01
Suggenhall Farm - Photovoltaic Solar Array & Battery Storage
RNA Energy Limited · DC/21/06825 · 28 mo to decide
7.3Awaiting Construction2024-04-17
Masons Landfill, Bramford Road, Great Blakenham - Solar Farm
Valencia Waster Management Limited · SCC/0083/22MS · 18.5 mo to decide
6.1Awaiting Construction2024-03-19
PPG, Letter Site - Solar Panels
PPG Industries (UK) Limited · DC/23/05743 · 3 mo to decide
0.43Awaiting Construction2024-03-14
Tye Lane - Solar Farm
EDF Energy Renewables · DC/21/04711 · 27.5 mo to decide
49.9Under Construction2023-12-18
The Grange Solar Farm & Battery Storage
Pathfinder Clean Energy UK Dev Limited · DC/22/02667 · 16.9 mo to decide
48Awaiting Construction2023-11-09
PPG Letter, Needham Road - Solar Pv Panels
PPG Industries · DC/23/03987 · 1.8 mo to decide
0.5Application Refused2023-10-16
Church Farm, The Channel - Bramford Solar Farm and Battery Storage
Bramford Green Limited · DC/23/02118 · 4.4 mo to decide
49.9Awaiting Construction2023-09-14
Bramford Solar Farm
Bramford Green · DC/21/00060 · 25.4 mo to decide
49.9Revised2023-02-17
Greybarn Solar Energy Farm
Statkraft UK · DC/22/01243
41.5Application Submitted2022-03-21
Roger Skinner - Solar panels
Roger Skinner Limited · DC/21/03850 · 0.9 mo to decide
0.58Awaiting Construction2021-09-02
Gainsborough Road Car Park - Solar PV arrays
Babergh & Mid Suffolk DC · DC/21/03600 · 2.2 mo to decide
0.19Awaiting Construction2021-09-01
Cranswick Country Foods
Cranswick Plc · DC/21/00610 · 2.9 mo to decide
1.5Awaiting Construction2021-04-29
Hill Farm (Baylham)
Hive Energy · 2801/13
10Application Withdrawn2014-06-06
Land at Hill Farm
Hive Energy · 3319/12
10Application Withdrawn2013-05-23
Mid Suffolk Home Solar Scheme
Mid Suffolk District Council
4.8Operational

Does Mid Suffolk approve solar farms?

Yes — of the 17 solar farms Mid Suffolk has decided, 88% were approved (15 granted, 2 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Mid Suffolk?

The median time from application to decision is 5.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Mid Suffolk consented?

246 MW has been consented across 15 approved schemes, with 1 MW refused. A further 4 applications awaits a decision.

Other technologies in Mid Suffolk

Battery storage in Mid SuffolkOnshore wind in Mid Suffolk

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report