Novarly ParcelRenewable planning

Renewable planning SolarInverclyde

Solar planning in Inverclyde

Inverclyde has decided 6 solar farms and approved 100% of them, taking a median of 2 months to decide. Consented capacity: 2 MW. 1 application still awaiting a decision.

100%
Approved
6 granted · 0 refused
2 mo
Median decision
UK 2.3 mo
2 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Inverclyde compares

Against the 298 UK authorities with 5+ solar decisions, Inverclyde sits in the 77th percentile for approval rate (7 points above the England average) and the 58th percentile for speed.

Decisions by year

35Approved — 3 (2022)322Approved — 1 (2023)123Approved — 1 (2024)124Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (7)

SchemeMWStatusDecided
Tesco Stores, Greenock Road - Solar PV System
Tesco Plc · 25/0011/CPL · 1.4 mo to decide
0.57Awaiting Construction2026-01-09
Knockair, Dougliehill Road - Solar Farm
Renewco Power · 25/0125/IC
25Application Submitted2025-08-20
Finlaystone House, Estate Greenock Road - Solar Panels
Finlaystone Country Estate · 24/0080/IC · 1.3 mo to decide
0.15Awaiting Construction2024-05-28
Overton Water Treatment Works, Old Largs Road By Overton - Solar Panels
Scottish Water Horizons · 22/0247/IC · 2.1 mo to decide
0.62Awaiting Construction2023-01-31
Greenock Headworks, Eldon Street - Solar Panels
Scottish Water Horizons · 22/0231/IC · 1.8 mo to decide
0.23Awaiting Construction2022-12-02
Faulds Park Road- Solar PV Panlels
Devol Engineering Limited · 22/0094/IC · 3 mo to decide
0.34Under Construction2022-07-20
King Street - Photovoltaic Panels
Inverclyde Council · 21/0262/IC · 6.8 mo to decide
Awaiting Construction2022-06-06

Does Inverclyde approve solar farms?

Yes — of the 6 solar farms Inverclyde has decided, 100% were approved (6 granted, 0 refused). The UK-wide rate for solar is 93%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a solar farm application take in Inverclyde?

The median time from application to decision is 2 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Inverclyde consented?

2 MW has been consented across 6 approved schemes. A further 1 application awaits a decision.

Other technologies in Inverclyde

Battery storage in InverclydeOnshore wind in Inverclyde

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.