Battery storage planning in Inverclyde
Inverclyde has decided 3 battery storage schemes and approved 100% of them, taking a median of 6.6 months to decide. Consented capacity: 104 MW. 3 applications still awaiting a decision.
⚠️ Small caseload (3 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Inverclyde compares
Against the 137 UK authorities with 5+ battery storage decisions, Inverclyde sits in the 73rd percentile for approval rate (8 points above the England average) and the 40th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (6)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Knockair, Dougliehill Road - Battery Storage Facility Renewco Power · 25/0125/IC | 24 | Application Submitted | 2025-08-20 |
Dougliehill Water Treatment Works, Dougliehill Road - Battery Storage Bluestone Energy · 25/0033/IC · 5.2 mo to decide | 49 | Awaiting Construction | 2025-08-06 |
Dougliehill Water Treatment Works, Dougliehill Road - Battery Storage Bluestone Energy · 24/0053/IC | 49 | Revised | 2024-09-27 |
Flatterton Farm, Flatterton Road - Battery Storage Big Battery (Flatterton Farm) Limited · 23/0205/IC · 7.9 mo to decide | 49.9 | Awaiting Construction | 2024-06-05 |
Kip Water Hydro Scheme Greenock Hydro Power · 18/0290/IC | 1 | Application Submitted | 2018-10-31 |
Berfern Farm Capbal · 18/0144/IC | 5 | Planning Permission Expired | 2018-05-14 |
Does Inverclyde approve battery storage schemes?
Yes — of the 3 battery storage schemes Inverclyde has decided, 100% were approved (3 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Inverclyde?
The median time from application to decision is 6.6 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Inverclyde consented?
104 MW has been consented across 3 approved schemes. A further 3 applications awaits a decision.
Other technologies in Inverclyde
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.