Novarly ParcelRenewable planning

Renewable planning SolarHyndburn

Solar planning in Hyndburn

Hyndburn has decided 12 solar farms and approved 100% of them, taking a median of 2.1 months to decide. Consented capacity: 5 MW. 4 applications still awaiting a decision.

100%
Approved
12 granted · 0 refused
2.1 mo
Median decision
UK 2.3 mo
5 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Hyndburn compares

Against the 298 UK authorities with 5+ solar decisions, Hyndburn sits in the 77th percentile for approval rate (7 points above the England average) and the 56th percentile for speed.

Decisions by year

35Approved — 2 (2021)221Approved — 2 (2022)222Approved — 1 (2023)123Approved — 5 (2024)524Approved — 1 (2025)125Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (16)

SchemeMWStatusDecided
Church Works, Bridge Street - Solar Panels
Private Developer · 11/26/0010 · 0.6 mo to decide
Awaiting Construction2026-01-27
Ramsclough Farm, Haslingden Old Road - Solar Farm
Abei Energy Limited · 11/26/0015
26.4Application Submitted2026-01-21
Mount Carmel RC High School, Wordsworth Road - Solar Panels
Mount Carmel High School · 11/25/0456 · 1.4 mo to decide
0.18Awaiting Construction2025-12-22
Mount Carmel RC High School, Wordsworth Road - Solar Panels
Mount Carmel High School · 11/25/0296 · 1.8 mo to decide
0.21Revised2025-10-03
Rhyddings Business And Enterprise School, Oswaldtwistle - Solar panels
Solar Options for Schools Limited · 11/24/0397 · 0.9 mo to decide
0.22Awaiting Construction2024-10-29
Senator International, Newhouse Road - Solar Photovoltaics Panels
Senator International Limited · 11/24/0226 · 1.1 mo to decide
0.3Awaiting Construction2024-07-03
Coach Road Meadow - Solar Farm
Prospects Community Energy Limited · 11/23/0180 · 13.1 mo to decide
2Awaiting Construction2024-06-14
Rhyddings Business And Enterprise School, Oswaldtwistle - Solar panels
Solar Options for Schools Limited · 11/24/0118 · 2.2 mo to decide
0.22Revised2024-05-20
The Hollins, Hollins Lane - Solar Panels
Solar Options for Schools Limited · 11/24/0095 · 1.1 mo to decide
0.33Awaiting Construction2024-04-08
Accrington and Rossendale College, Sandy Lane - Solar PV Panels
Nelson & Colne College · 11/23/0412 · 3.1 mo to decide
0.43Awaiting Construction2024-02-02
St Christophers School, Queens Road - Solar Panels
Solar Options for Schools Limited · 11/23/0166 · 2.1 mo to decide
0.41Awaiting Construction2023-06-15
Altham Business Park - Solar Panels
The Senator Group Altham · 11/21/0596 · 14.6 mo to decide
1.18Operational2022-12-16
Altham - Solar PV
Senator Group · 11/21/0674 · 11 mo to decide
0.15Awaiting Construction2022-01-14
Whinney Hill Road - Solar Photovoltaic Panels
Senator Group · 11/21/0675 · 2.5 mo to decide
0.18Awaiting Construction2021-12-02
Newhouse Road - Solar PV System
Senator Group · 11/21/0673
0.43Application Submitted2021-02-12
Whitebirk Depot Solar Panels
Electricity North West Limited · 11/20/0420 · 2.4 mo to decide
Awaiting Construction2021-01-28

Does Hyndburn approve solar farms?

Yes — of the 12 solar farms Hyndburn has decided, 100% were approved (12 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Hyndburn?

The median time from application to decision is 2.1 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Hyndburn consented?

5 MW has been consented across 12 approved schemes. A further 4 applications awaits a decision.

Other technologies in Hyndburn

Battery storage in HyndburnOnshore wind in Hyndburn

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com