Battery storage planning in Hyndburn

Hyndburn has decided 1 battery storage scheme and approved 100% of them, taking a median of 3.1 months to decide. Consented capacity: 1 MW.

100%
Approved
1 granted · 0 refused
3.1 mo
Median decision
UK 6 mo
1 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (1 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Hyndburn compares

Against the 137 UK authorities with 5+ battery storage decisions, Hyndburn sits in the 73rd percentile for approval rate (8 points above the England average) and the 85th percentile for speed.

Every recorded scheme (1)

SchemeMWStatusDecided
Accrington and Rossendale College, Sandy Lane - Battery Storage
Nelson & Colne College · 11/23/0412 · 3.1 mo to decide
1Awaiting Construction2024-02-02

Does Hyndburn approve battery storage schemes?

Yes — of the 1 battery storage schemes Hyndburn has decided, 100% were approved (1 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Hyndburn?

The median time from application to decision is 3.1 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Hyndburn consented?

1 MW has been consented across 1 approved scheme. There are no applications currently awaiting a decision.

Other technologies in Hyndburn

Solar in HyndburnOnshore wind in Hyndburn

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.