Solar planning in Halton

Halton has decided 6 solar farms and approved 83% of them, taking a median of 3.7 months to decide. Consented capacity: 5 MW. 4 applications still awaiting a decision.

83%
Approved
5 granted · 1 refused
3.7 mo
Median decision
UK 2.3 mo
5 MW
Consented
3 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Halton compares

Against the 298 UK authorities with 5+ solar decisions, Halton sits in the 12th percentile for approval rate (10 points below the England average) and the 19th percentile for speed.

Decisions by year

35Approved — 1 (2022)Refused — 1 (2022)222Approved — 1 (2023)123Approved — 2 (2024)224Approved — 1 (2025)125
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (11)

SchemeMWStatusDecided
Ditton Road - Solar Microgrid
Halton Borough Council · 24/00234/HBCFUL · 7.2 mo to decide
4Awaiting Construction2025-01-23
Sutton International, Gorsey Lane - Solar PV Arrays
SNRG · 24/00407/PRIOR · 1.2 mo to decide
Awaiting Construction2024-12-05
Hosokawa Micron, Rivington Road - Solar Panels
Hosokawa Micron Limited · 24/00056/PRIOR · 1.8 mo to decide
0.43Awaiting Construction2024-04-02
Phoenix Medical Supplies, Rivington Road - Solar Panels
Phoenix Medical Supplies · 23/00001/PRIOR · 1.6 mo to decide
0.24Awaiting Construction2023-02-07
Liverpool John Lennon Airport - Solar Farm
Liverpool Airport Limited · 22/00019/PLD · 6.1 mo to decide
3Application Refused2022-06-29
Hedco, Desoto Road - Solar panels
PSD Construct Limtied · 22/00276/FUL
3.5Application Submitted2022-05-27
Daresbury Science Park - Solar Array
Science and Technology Facilities Council · 21/00475/FUL · 5.5 mo to decide
0.56Operational2022-01-19
John Lennon Airport Scheme
Liverpool John Lennon Airport Plc · 21/00310/PLD
3Revised2021-09-14
John Lennon Airport Scheme
Peel Energy · 18/00513/FUL
3Revised2019-06-27
Johnson's Lane - Halton
SBC Renewables · 15/00332/FUL · 3.7 mo to decide
3.5Abandoned2015-10-21
Johnson's Lane
SBC Renewables · 15/00060/FUL
5Revised2015-04-29

Does Halton approve solar farms?

Yes — of the 6 solar farms Halton has decided, 83% were approved (5 granted, 1 refused). The UK-wide rate for solar is 93%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a solar farm application take in Halton?

The median time from application to decision is 3.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Halton consented?

5 MW has been consented across 5 approved schemes, with 3 MW refused. A further 4 applications awaits a decision.

Other technologies in Halton

Battery storage in HaltonOnshore wind in Halton

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com