Battery storage planning in Halton
Halton has decided 3 battery storage schemes and approved 100% of them, taking a median of 10.3 months to decide. Consented capacity: 164 MW.
⚠️ Small caseload (3 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Halton compares
Against the 137 UK authorities with 5+ battery storage decisions, Halton sits in the 73rd percentile for approval rate (8 points above the England average) and the 11th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (3)
| Scheme | MW | Status | Decided |
|---|---|---|---|
St Michaels Road, Ditton Road - Battery Storage Shell Green Limited · 22/00623/FUL · 10.9 mo to decide | 14 | Awaiting Construction | 2023-10-27 |
Cholmondeley Road - Battery Storage P3P Partners LLP · 21/00565/FUL · 10.3 mo to decide | 150 | Awaiting Construction | 2022-08-10 |
Leiria Way Car Park Entrust Microgrid · 20/00079/FUL · 2.5 mo to decide | — | Operational | 2020-05-05 |
Does Halton approve battery storage schemes?
Yes — of the 3 battery storage schemes Halton has decided, 100% were approved (3 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Halton?
The median time from application to decision is 10.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Halton consented?
164 MW has been consented across 3 approved schemes. There are no applications currently awaiting a decision.
Other technologies in Halton
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.