Solar planning in Fareham

Fareham has decided 6 solar farms and approved 100% of them, taking a median of 1.8 months to decide. Consented capacity: 25 MW. 1 application still awaiting a decision.

100%
Approved
6 granted · 0 refused
1.8 mo
Median decision
UK 2.3 mo
25 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Fareham compares

Against the 298 UK authorities with 5+ solar decisions, Fareham sits in the 77th percentile for approval rate (7 points above the England average) and the 74th percentile for speed.

Decisions by year

35Approved — 1 (2013)113Approved — 1 (2020)120Approved — 1 (2021)121Approved — 1 (2023)123Approved — 2 (2024)224
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (7)

SchemeMWStatusDecided
Fareham leisure centre, Park Lane - Solar Panels
Fareham Borough Council · P/24/1228/PA · 1.7 mo to decide
0.25Awaiting Construction2024-11-11
ATS, Sopwith Way - Ground Mounted Solar Photovoltaic Arrays
NATS · P/23/1267/FP · 8.8 mo to decide
3.27Awaiting Construction2024-06-11
National Air Traffic Services, Sopwith Way - Solar Panels
NATS Limited · P/23/0957/PA · 1.7 mo to decide
0.99Awaiting Construction2023-08-31
Hoads Hill Reservoir - Solar Panels
Portsmouth Water · P/21/1239/LP · 1.8 mo to decide
0.16Awaiting Construction2021-09-13
Tesco Quay Street
Push Energy · P/20/0010/PA · 0.9 mo to decide
0.3Awaiting Construction2020-02-03
Newlands Farm Solar
Sunsave 10 (FAREHAM) / Vogt Solar · P/13/0528/FP · 3 mo to decide
20.5Operational2013-09-27
Newlands Farm Solar
Sunsave 10 (FAREHAM) / Vogt Solar · P/12/0905/FP
49Revised2013-02-13

Does Fareham approve solar farms?

Yes — of the 6 solar farms Fareham has decided, 100% were approved (6 granted, 0 refused). The UK-wide rate for solar is 93%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a solar farm application take in Fareham?

The median time from application to decision is 1.8 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Fareham consented?

25 MW has been consented across 6 approved schemes. A further 1 application awaits a decision.

Other technologies in Fareham

Battery storage in FarehamOnshore wind in Fareham

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.