Solar planning in Dundee City
Dundee City has decided 5 solar farms and approved 100% of them, taking a median of 2.3 months to decide. Consented capacity: 52 MW. 1 application still awaiting a decision.
⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Dundee City compares
Against the 298 UK authorities with 5+ solar decisions, Dundee City sits in the 77th percentile for approval rate (7 points above the England average) and the 51st percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (7)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Police Station, Balunie Drive - Solar PV Array Scottish Police Authority · 22/00658/FULL · 2.8 mo to decide | 0.16 | Awaiting Construction | 2023-01-25 |
Harris Academy, Perth Road - Soalr Panels Dundee City Council · 22/00802/FULL · 1.4 mo to decide | 0.18 | Awaiting Construction | 2023-01-12 |
Grange Of Berryhill - Solar Farm Uniper UK Limited · 21/00535/FULM · 14.3 mo to decide | 49.9 | Awaiting Construction | 2022-09-21 |
Harris Academy, Perth Road - Extension/Roof Solar Photovoltaic Array Dundee City Council · 22/00456/FULL · 1.2 mo to decide | — | Under Construction | 2022-08-16 |
Harris Academy, Perth Road - Solar Photovoltaic array Dundee City Council · 22/00304/FULL | 0.19 | Revised | 2022-04-18 |
Dykes Of Gray Road - Solar PV Array Dundee Renewable Energy Society · 21/00670/FULL · 6.1 mo to decide | 2 | Awaiting Construction | 2022-03-16 |
Michelin Tyres McLaughlin and Harvey · 16/00190/FULL · 1.8 mo to decide | — | Abandoned | 2016-03-31 |
Does Dundee City approve solar farms?
Yes — of the 5 solar farms Dundee City has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for solar is 93%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a solar farm application take in Dundee City?
The median time from application to decision is 2.3 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has Dundee City consented?
52 MW has been consented across 5 approved schemes. A further 1 application awaits a decision.
Other technologies in Dundee City
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.