Battery storage planning in Dover

Dover has decided 4 battery storage schemes and approved 100% of them, taking a median of 6.1 months to decide. Consented capacity: 60 MW. 1 application still awaiting a decision.

100%
Approved
4 granted · 0 refused
6.1 mo
Median decision
UK 6 mo
60 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Dover compares

Against the 137 UK authorities with 5+ battery storage decisions, Dover sits in the 73rd percentile for approval rate (8 points above the England average) and the 45th percentile for speed.

Decisions by year

35Approved — 2 (2022)222Approved — 1 (2023)123Approved — 1 (2024)124
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (5)

SchemeMWStatusDecided
Elvington Battery Energy Storage
Pathfinder Clean Energy UK Limited · 25/00709
49.5Application Submitted2025-06-21
Wharf Road, Discovery Park - Battery Energy Storage
Kent Renewable Energy Limited · 23/01446 · 9.6 mo to decide
10Awaiting Construction2024-11-11
Aylesham And District Community Workshop, Ackholt Road - Battery Storage
AMP Clean Energy · 23/01090 · 1.6 mo to decide
0.2Awaiting Construction2023-10-20
Harrington Franklin, Richborough Energy Park - Battery Storage
EDP Renewables · 22/00705 · 6.2 mo to decide
49.9Under Construction2022-12-06
Chalk Pit Solar Farm
Greentech Services · 22/00668 · 6.1 mo to decide
Under Construction2022-11-25

Does Dover approve battery storage schemes?

Yes — of the 4 battery storage schemes Dover has decided, 100% were approved (4 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Dover?

The median time from application to decision is 6.1 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Dover consented?

60 MW has been consented across 4 approved schemes. A further 1 application awaits a decision.

Other technologies in Dover

Solar in DoverOnshore wind in Dover

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.