Renewable planning › Battery storage › Wirral
Battery storage planning in Wirral
Wirral has decided 4 battery storage schemes and approved 100% of them, taking a median of 1.6 months to decide. Consented capacity: 32 MW.
⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Wirral compares
Against the 137 UK authorities with 5+ battery storage decisions, Wirral sits in the 73rd percentile for approval rate (8 points above the England average) and the 99th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (5)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Biffa Waste Services, Dock Road South - Battery Storage Units Biffa Waste Services Limited · APP/22/01570 · 0.8 mo to decide | — | Awaiting Construction | 2022-12-07 |
Eastham Balacing Services Plant Peel Land and Property · APP/17/01243 | 27 | Application Withdrawn | 2018-04-04 |
Britannia House Peel Energy · APP/17/01190 · 2.5 mo to decide | 10 | Planning Permission Expired | 2017-12-04 |
Burbo Bank Energy Storage �rsted · APP/17/00463 | 2 | Operational | 2017-04-14 |
Beaufort Road UK Power Reserve · APP/16/01212 | 20 | Planning Permission Expired | 2016-09-05 |
Does Wirral approve battery storage schemes?
Yes — of the 4 battery storage schemes Wirral has decided, 100% were approved (4 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Wirral?
The median time from application to decision is 1.6 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Wirral consented?
32 MW has been consented across 4 approved schemes. There are no applications currently awaiting a decision.
Other technologies in Wirral
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com
Screen a specific site here · All authorities · UK property report