Battery storage planning in Southampton

Southampton has decided 2 battery storage schemes and approved 50% of them, taking a median of 14.4 months to decide. Consented capacity: 99 MW.

50%
Approved
1 granted · 1 refused
14.4 mo
Median decision
UK 6 mo
99 MW
Consented
50 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (2 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Southampton compares

Against the 137 UK authorities with 5+ battery storage decisions, Southampton sits in the 1st percentile for approval rate (42 points below the England average) and the 4th percentile for speed.

Decisions by year

35Approved — 1 (2024)124Refused — 1 (2025)125
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (2)

SchemeMWStatusDecided
Weston Lane - Battery Storage Facility
Anglo Renewables Limited · 23/03055/FULLS · 18.4 mo to decide
49.9Application Refused2025-06-12
Butts Field, Mill Lane - Battery Storage
Ecotricity Generation Limited · 23/02942/FULLS · 10.3 mo to decide
99Awaiting Construction2024-10-03

Does Southampton approve battery storage schemes?

Yes — of the 2 battery storage schemes Southampton has decided, 50% were approved (1 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Southampton?

The median time from application to decision is 14.4 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Southampton consented?

99 MW has been consented across 1 approved scheme, with 50 MW refused. There are no applications currently awaiting a decision.

Other technologies in Southampton

Solar in SouthamptonOnshore wind in Southampton

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.