Novarly ParcelRenewable planning

Renewable planning Battery storageSouth Ribble

Battery storage planning in South Ribble

South Ribble has decided 4 battery storage schemes and approved 100% of them, taking a median of 1.7 months to decide. Consented capacity: 112 MW. 1 application still awaiting a decision.

100%
Approved
4 granted · 0 refused
1.7 mo
Median decision
UK 6 mo
112 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How South Ribble compares

Against the 137 UK authorities with 5+ battery storage decisions, South Ribble sits in the 73rd percentile for approval rate (8 points above the England average) and the 99th percentile for speed.

Decisions by year

35Approved — 1 (2020)120Approved — 1 (2021)121Approved — 1 (2022)122Approved — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (5)

SchemeMWStatusDecided
Moss Side Way - Micro Energy Storage
AMP Clean Energy · 07/2025/00981/FUL · 1.9 mo to decide
0.2Awaiting Construction2026-02-09
Penwortham - Battery storage
Shaw-Energi Limited · 07/2022/00021/FUL · 0.9 mo to decide
57Awaiting Construction2022-04-29
Penwortham Sub Station
Statera Energy · 07/2017/2821/FUL · 43.8 mo to decide
50Planning Permission Expired2021-05-14
Howick Hall Farm - Battery Storage Facility
Penwortham Storage Limited · 07/2021/00252/FUL
49.9Application Submitted2021-01-21
The Glowhouse
AMP Clean Energy · 07/2020/00739/FUL · 1.4 mo to decide
5Under Construction2020-10-21

Does South Ribble approve battery storage schemes?

Yes — of the 4 battery storage schemes South Ribble has decided, 100% were approved (4 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in South Ribble?

The median time from application to decision is 1.7 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has South Ribble consented?

112 MW has been consented across 4 approved schemes. A further 1 application awaits a decision.

Other technologies in South Ribble

Solar in South RibbleOnshore wind in South Ribble

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com