Battery storage planning in Sefton

Sefton has decided 4 battery storage schemes and approved 100% of them, taking a median of 5 months to decide. Consented capacity: 20 MW. 2 applications still awaiting a decision.

100%
Approved
4 granted · 0 refused
5 mo
Median decision
UK 6 mo
20 MW
Consented
across approved schemes
1
Appeals
1 allowed on appeal

⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Sefton compares

Against the 137 UK authorities with 5+ battery storage decisions, Sefton sits in the 73rd percentile for approval rate (8 points above the England average) and the 62nd percentile for speed.

Decisions by year

35Approved — 1 (2018)118Approved — 2 (2022)222Approved — 1 (2025)125
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (6)

SchemeMWStatusDecided
Rowan View Hospital, Villas Road - Battery Storage
Mersey Care NHS Trust · DC/2025/01589
Application Submitted2025-11-28
Rowan View Hospital, Villas Road - Battery Storage
Mersey Care NHS Trust · DC/2025/01286
Revised2025-09-25
Heysham Box, Leckwith Road - Battery Storage
AMP Clean Energy · DC/2025/00080 · 1.3 mo to decide
0.2Awaiting Construction2025-03-04
Heysham Box, Leckwith Road - Battery Storage
AMP Clean Energy · DC/2022/01871 · 1.8 mo to decide
0.2Awaiting Construction2022-11-16
Hawthorne Road
Bluefield Renewable Developments · DC/2020/00085 · 26 mo to decide
20Under Construction2022-03-29
Peel Road Energy Centre
Suncredit · 17/0822 · 8.2 mo to decide
Planning Permission Expired2018-06-04

Does Sefton approve battery storage schemes?

Yes — of the 4 battery storage schemes Sefton has decided, 100% were approved (4 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Sefton?

The median time from application to decision is 5 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Sefton consented?

20 MW has been consented across 4 approved schemes. A further 2 applications awaits a decision.

Other technologies in Sefton

Solar in SeftonOnshore wind in Sefton

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.