Onshore wind planning in Sefton

Sefton has decided 2 onshore wind schemes and approved 100% of them, taking a median of 13 months to decide. Consented capacity: 13 MW.

100%
Approved
2 granted · 0 refused
13 mo
Median decision
UK 11.5 mo
13 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (2 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Sefton compares

Against the 75 UK authorities with 5+ onshore wind decisions, Sefton sits in the 98th percentile for approval rate (32 points above the England average) and the 55th percentile for speed.

Every recorded scheme (2)

SchemeMWStatusDecided
Port of Liverpool - wind
Mersey Docks and Harbour Company · 05F/2712 · 3.7 mo to decide
10Operational2005-12-08
Royal Seaforth Dock Wind Farm
Mersey Docks and Harbour Company and Windcluster Limited · 22.3 mo to decide
3Operational1997-08-22

Does Sefton approve onshore wind schemes?

Yes — of the 2 onshore wind schemes Sefton has decided, 100% were approved (2 granted, 0 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Sefton?

The median time from application to decision is 13 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Sefton consented?

13 MW has been consented across 2 approved schemes. There are no applications currently awaiting a decision.

Other technologies in Sefton

Solar in SeftonBattery storage in Sefton

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.