Battery storage planning in Scottish Borders

Scottish Borders has decided 4 battery storage schemes and approved 75% of them, taking a median of 10.2 months to decide. Consented capacity: 180 MW. 1 application still awaiting a decision.

75%
Approved
3 granted · 1 refused
10.2 mo
Median decision
UK 6 mo
180 MW
Consented
across approved schemes
1
Appeals
0 allowed on appeal

⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Scottish Borders compares

Against the 137 UK authorities with 5+ battery storage decisions, Scottish Borders sits in the 7th percentile for approval rate (17 points below the England average) and the 12th percentile for speed.

Decisions by year

35Approved — 1 (2019)119Approved — 1 (2023)123Refused — 1 (2024)124Approved — 1 (2025)125
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (5)

SchemeMWStatusDecided
Keepers House, Byrecleugh - Battery Energy Storage
Sunlaws Development Company Limited · 25/00374/FUL · 8.2 mo to decide
49.5Awaiting Construction2025-12-08
Wull Muir Wind Farm
Energiekontor UK Limited · 22/01960/FUL · 18.7 mo to decide
Application Refused2024-07-08
Eccles Substation, Eccles - Battery Energy Storage System
Eccles Grid Stability Limited · 22/01988/FUL · 5.7 mo to decide
50Under Construction2023-06-15
Wull Muir Wind Farm
EnergieKontor UK · 19/00191/FUL · 10.2 mo to decide
4Revised2020-02-05
Aikengall II Community Wind Farm Battery
Community Wind Power · 18/00865/P · 12.5 mo to decide
80Operational2019-01-25

Does Scottish Borders approve battery storage schemes?

Yes — of the 4 battery storage schemes Scottish Borders has decided, 75% were approved (3 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Scottish Borders?

The median time from application to decision is 10.2 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Scottish Borders consented?

180 MW has been consented across 3 approved schemes. A further 1 application awaits a decision.

Other technologies in Scottish Borders

Solar in Scottish BordersOnshore wind in Scottish Borders

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.