Novarly ParcelRenewable planning

Renewable planning Onshore windOldham

Onshore wind planning in Oldham

Oldham has decided 1 onshore wind scheme and approved 0% of them, taking a median of 26.7 months to decide.

0%
Approved
0 granted · 1 refused
26.7 mo
Median decision
UK 11.5 mo
0 MW
Consented
11 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (1 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Oldham compares

Against the 75 UK authorities with 5+ onshore wind decisions, Oldham sits in the 0th percentile for approval rate (68 points below the England average) and the 8th percentile for speed.

Every recorded scheme (1)

SchemeMWStatusDecided
Denshaw Windfarm
E. ON UK Renewables · PA46136-03 · 26.7 mo to decide
10.5Application Refused2006-02-23

Does Oldham approve onshore wind schemes?

Yes — of the 1 onshore wind schemes Oldham has decided, 0% were approved (0 granted, 1 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Oldham?

The median time from application to decision is 26.7 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Oldham consented?

0 MW has been consented across 0 approved schemes, with 11 MW refused. There are no applications currently awaiting a decision.

Other technologies in Oldham

Solar in OldhamBattery storage in Oldham

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report