Renewable planning › Battery storage › Fermanagh and Omagh
Battery storage planning in Fermanagh and Omagh
Fermanagh and Omagh has decided 3 battery storage schemes and approved 100% of them, taking a median of 11.3 months to decide. Consented capacity: 90 MW. 4 applications still awaiting a decision.
⚠️ Small caseload (3 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Fermanagh and Omagh compares
Against the 137 UK authorities with 5+ battery storage decisions, Fermanagh and Omagh sits in the 73rd percentile for approval rate (8 points above the England average) and the 9th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (7)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Cavan Road - Battery Energy Storage System Electric Land · LA10/2024/0866/F · 10.3 mo to decide | — | Awaiting Construction | 2025-07-29 |
Battery Energy Storage System Development in Tyrone Heron Storage Limited · LA10/2024/0294/F · 11.3 mo to decide | 50 | Awaiting Construction | 2025-03-20 |
Skreen Road - Battery Energy Storage System Renewable Energy Systems Ltd · LA10/2025/0003/F | 100 | Application Submitted | 2024-12-20 |
Doogary Road, Omagh - Battery Storage Omagh BES Limited · LA10/2023/1605/F · 20.5 mo to decide | 40 | Awaiting Construction | 2024-12-13 |
Battery Energy Storage System Development in Drumquin Lightsource Renewable Energy Ireland Limited · LA10/2024/1111/F | 87.8 | Application Submitted | 2024-11-15 |
Gort Energy Storage ENGIE Renewables · LA10/2020/0206/F | — | Application Submitted | 2020-02-27 |
Classic Marble Showers Site Engie Developments Ireland · LA10/2018/1589/F | 48 | Revised | 2018-12-18 |
Does Fermanagh and Omagh approve battery storage schemes?
Yes — of the 3 battery storage schemes Fermanagh and Omagh has decided, 100% were approved (3 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Fermanagh and Omagh?
The median time from application to decision is 11.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Fermanagh and Omagh consented?
90 MW has been consented across 3 approved schemes. A further 4 applications awaits a decision.
Other technologies in Fermanagh and Omagh
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.