Novarly ParcelRenewable planning

Renewable planning Battery storageEast Renfrewshire

Battery storage planning in East Renfrewshire

East Renfrewshire has decided 1 battery storage scheme and approved 100% of them, taking a median of 4.3 months to decide. Consented capacity: 40 MW. 1 application still awaiting a decision.

100%
Approved
1 granted · 0 refused
4.3 mo
Median decision
UK 6 mo
40 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (1 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How East Renfrewshire compares

Against the 137 UK authorities with 5+ battery storage decisions, East Renfrewshire sits in the 73rd percentile for approval rate (8 points above the England average) and the 71st percentile for speed.

Every recorded scheme (2)

SchemeMWStatusDecided
Glasgow Road, Eaglesham - Battery Storage Facility
GPC 1137 Limited (Apatura) · 2025/0043/TP · 2.7 mo to decide
40Awaiting Construction2025-04-15
Glasgow Road, Eaglesham - Battery Storage Facility
GPC 1137 Limited · 2024/0168/TP · 6 mo to decide
40Revised2024-10-31

Does East Renfrewshire approve battery storage schemes?

Yes — of the 1 battery storage schemes East Renfrewshire has decided, 100% were approved (1 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in East Renfrewshire?

The median time from application to decision is 4.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has East Renfrewshire consented?

40 MW has been consented across 1 approved scheme. A further 1 application awaits a decision.

Other technologies in East Renfrewshire

Solar in East RenfrewshireOnshore wind in East Renfrewshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.