Burnley has decided 4 battery storage schemes and approved 50% of them, taking a median of 6.5 months to decide. Consented capacity: 70 MW. 3 applications still awaiting a decision.

50%
Approved
2 granted · 2 refused
6.5 mo
Median decision
UK 6 mo
70 MW
Consented
145 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Burnley compares

Against the 137 UK authorities with 5+ battery storage decisions, Burnley sits in the 1st percentile for approval rate (42 points below the England average) and the 40th percentile for speed.

Decisions by year

35Approved — 2 (2023)223Refused — 2 (2024)224
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (7)

SchemeMWStatusDecided
Padiham - Battery Energy Storage
Energi Generation Limited · FUL/2024/0258 · 6.5 mo to decide
99.9Application Refused2024-12-16
Huncoat Power Station - Battery Storage Facility
Newgen Limited · FUL/2023/0785 · 10.1 mo to decide
45Application Refused2024-10-31
Huncoat Power Station - Battery Storage Facility
24 Power Limited · FUL/2022/0729
45Revised2023-12-15
Former Bull & Butcher Pub - Battery Energy Storage
LNT Care Developments · FUL/2023/0263 · 1.6 mo to decide
Awaiting Construction2023-07-31
Widow Hill, Balderstone Lane - Battery Energy Storage System
P3P Partners LLP · FUL/2021/0375 · 24.2 mo to decide
70Under Construction2023-07-20
he Yard, Holme Road, Burnley - Battery Storeage
Larkfleet Group · FUL/2022/0703
Application Submitted2022-12-02
Huncoat Power Station - Battery Storage
24 Power Limited · FUL/2021/0601 · 3 mo to decide
50Revised2022-01-18

Does Burnley approve battery storage schemes?

Yes — of the 4 battery storage schemes Burnley has decided, 50% were approved (2 granted, 2 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Burnley?

The median time from application to decision is 6.5 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Burnley consented?

70 MW has been consented across 2 approved schemes, with 145 MW refused. A further 3 applications awaits a decision.

Other technologies in Burnley

Solar in BurnleyOnshore wind in Burnley

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report