Renewable planning Onshore windBolsover

Onshore wind planning in Bolsover

Bolsover has decided 2 onshore wind schemes and approved 0% of them, taking a median of 21.4 months to decide.

0%
Approved
0 granted · 2 refused
21.4 mo
Median decision
UK 11.5 mo
0 MW
Consented
17 MW refused
1
Appeals
0 allowed on appeal

⚠️ Small caseload (2 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Bolsover compares

Against the 75 UK authorities with 5+ onshore wind decisions, Bolsover sits in the 0th percentile for approval rate (68 points below the UK average) and the 14th percentile for speed.

Screening a site of your own?

RedlineUK · £39

Bolsover approves 0% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site£39
Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Every recorded scheme (2)

SchemeMWStatusDecided
Roseland Community Wind Farm
Roseland Community Energy Trust · 12/00159/FULEA · 14.8 mo to decide
12Application Refused2013-07-19
Losk Lane
Banks Development · 10/00463/FULEA · 28.1 mo to decide
5Application Refused2013-02-01

Does Bolsover approve onshore wind schemes?

Yes — of the 2 onshore wind schemes Bolsover has decided, 0% were approved (0 granted, 2 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Bolsover?

The median time from application to decision is 21.4 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Bolsover consented?

0 MW has been consented across 0 approved schemes, with 17 MW refused. There are no applications currently awaiting a decision.

Other technologies in Bolsover

Solar in BolsoverBattery storage in Bolsover

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.