Battery storage planning in Blackburn with Darwen

Blackburn with Darwen has decided 3 battery storage schemes and approved 100% of them, taking a median of 6.9 months to decide. Consented capacity: 25 MW.

100%
Approved
3 granted · 0 refused
6.9 mo
Median decision
UK 6 mo
25 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (3 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Blackburn with Darwen compares

Against the 137 UK authorities with 5+ battery storage decisions, Blackburn with Darwen sits in the 73rd percentile for approval rate (8 points above the England average) and the 36th percentile for speed.

Decisions by year

35Approved — 1 (2021)121Approved — 1 (2022)122Approved — 1 (2024)124
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (3)

SchemeMWStatusDecided
Gladstone Street, Little Harwood - Battery Energy Storage Facility
Conrad Energy (Developments) Limited · 10/24/0208 · 1.9 mo to decide
Awaiting Construction2024-05-01
Davies Road - Whitebirk Battery Storage
Field · 11/21/0483 · 6.9 mo to decide
25Awaiting Construction2022-03-02
Balle Street
STOR Power · 10/17/1198 · 48.9 mo to decide
Under Construction2021-11-05

Does Blackburn with Darwen approve battery storage schemes?

Yes — of the 3 battery storage schemes Blackburn with Darwen has decided, 100% were approved (3 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Blackburn with Darwen?

The median time from application to decision is 6.9 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Blackburn with Darwen consented?

25 MW has been consented across 3 approved schemes. There are no applications currently awaiting a decision.

Other technologies in Blackburn with Darwen

Solar in Blackburn with DarwenOnshore wind in Blackburn with Darwen

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.