Renewable planning › Onshore wind › Blackburn with Darwen
Onshore wind planning in Blackburn with Darwen
Blackburn with Darwen has decided 1 onshore wind scheme and approved 0% of them, taking a median of 10.6 months to decide. 2 applications still awaiting a decision.
⚠️ Small caseload (1 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Blackburn with Darwen compares
Against the 75 UK authorities with 5+ onshore wind decisions, Blackburn with Darwen sits in the 0th percentile for approval rate (68 points below the England average) and the 70th percentile for speed.
Every recorded scheme (4)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Hoddlesdon Moss Viridis Wind Turbines · 10/16/0704 | 2.7 | Application Withdrawn | 2017-04-25 |
Hoddlesden Moss Viridis Wind Turbines · 10/14/1117 · 6.1 mo to decide | 2.4 | Revised | 2015-04-21 |
Hoddlesden Moss Viridis Wind Turbines · 10/13/0829 | 2.4 | Revised | 2014-01-02 |
The Stables (Edgeworth) Private Developer · 10/03/0689 · 15.1 mo to decide | 2.6 | Application Refused | 2004-10-21 |
Does Blackburn with Darwen approve onshore wind schemes?
Yes — of the 1 onshore wind schemes Blackburn with Darwen has decided, 0% were approved (0 granted, 1 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a onshore wind scheme application take in Blackburn with Darwen?
The median time from application to decision is 10.6 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Blackburn with Darwen consented?
0 MW has been consented across 0 approved schemes, with 3 MW refused. A further 2 applications awaits a decision.
Other technologies in Blackburn with Darwen
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com