Renewable sites › Triton Knoll�
Triton Knoll�
Triton Knoll� is operational in England with a recorded capacity of 857 MW, and has been generating since 2022-01-13.
Planning and build timeline
| Application submitted | 2012-02-24 |
| Permission granted | 2013-07-11 17 months after submission |
| Operational | 2022-01-13 102 months after consent |
What this site sits on
- Special Area of Conservation — Inner Dowsing, Race Bank and North Ridge
- Special Protection Area — Greater Wash
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
How big is Triton Knoll�?
Triton Knoll� has a recorded installed capacity of 857 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Triton Knoll�?
REPD records the operator as Innogy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Triton Knoll� approved and built?
The application was submitted on 2012-02-24. Permission was granted on 2013-07-11, 17 months later. The site became operational on 2022-01-13, 102 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2532.