Torbay Leisure Centre - Energy Project is under construction in Torbay with a recorded capacity of 0.17 MW.

0.17 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Leisure Energy
Torbay
Authority
England

Planning and build timeline

Application submitted2022-02-03
Permission granted2022-03-11
1 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Blackawton Solar Farm
Solar Photovoltaics · Operational
38.6 km
Rydon Farm
Solar Photovoltaics · Operational
1210.4 km
Land at Oldstone Farm
Solar Photovoltaics · Operational
510.6 km
Bidwell Solar Farm
Solar Photovoltaics · Operational
511.9 km
Hazard Farm
Solar Photovoltaics · Operational
6.413.9 km
Place Barton Farm
Solar Photovoltaics · Operational
4.914.7 km
Coombeshead Solar Farm
Solar Photovoltaics · Operational
814.9 km

How big is Torbay Leisure Centre - Energy Project?

Torbay Leisure Centre - Energy Project has a recorded installed capacity of 0.17 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Torbay Leisure Centre - Energy Project?

REPD records the operator as Leisure Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Torbay Leisure Centre - Energy Project approved and built?

The application was submitted on 2022-02-03. Permission was granted on 2022-03-11, 1 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10654.