Shetland Tidal Array is operational in Scotland with a recorded capacity of 0.5 MW, and has been generating since 2019-06-24.

0.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2019-06-24
Tidal Stream
Technology
Nova Innovation
National
Authority
Scotland

Planning and build timeline

Application submitted2018-02-01
Permission grantednot recorded
Operational2019-06-24

Other built sites within 15 km

SiteMWDistance
Shetland Tidal Array (extension)
Tidal Stream · Operational
1.40 km

How big is Shetland Tidal Array?

Shetland Tidal Array has a recorded installed capacity of 0.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Shetland Tidal Array?

REPD records the operator as Nova Innovation. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Shetland Tidal Array approved and built?

The application was submitted on 2018-02-01. REPD does not record a grant date. The site became operational on 2019-06-24.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6637.