Sheringham Shoal� is operational in DECC (S36) with a recorded capacity of 317 MW, and has been generating since 2012-10-29.

317 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-10-29
Wind Offshore
Technology
Equinor
DECC (S36)
Authority
England

Planning and build timeline

Application submitted2006-05-30
Permission granted2008-08-07
26 months after submission
Operational2012-10-29
51 months after consent

How big is Sheringham Shoal�?

Sheringham Shoal� has a recorded installed capacity of 317 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Sheringham Shoal�?

REPD records the operator as Equinor. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Sheringham Shoal� approved and built?

The application was submitted on 2006-05-30. Permission was granted on 2008-08-07, 26 months later. The site became operational on 2012-10-29, 51 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2512.