Seamer Carr

Seamer Carr is an operational 1.3 MW landfill gas site in North Yorkshire, generating since 15 March 2000. Planning permission was granted on 23 September 1999, 4 months after submission. Operator of record: Yorwaste.

1.3 MW
Capacity
as recorded in REPD
Operational
Status
since 15 March 2000
Landfill Gas
Technology
Yorwaste
North Yorkshire
Authority
England

Planning and build timeline

Application submitted11 May 1999
Permission granted23 September 1999
4 months after submission
Operational15 March 2000
6 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in North Yorkshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Seamer Carr’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
322.5 km
Solar Photovoltaics · Operational
58.8 km

How big is Seamer Carr?

Seamer Carr has a recorded installed capacity of 1.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Seamer Carr?

REPD records the operator as Yorwaste. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Seamer Carr approved and built?

The application was submitted on 11 May 1999. Permission was granted on 23 September 1999, 4 months later. The site became operational on 15 March 2000, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 761.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode