Novarly ParcelRenewable sites

Renewable sitesSeagreen

Seagreen

Seagreen is an operational 1.07 GW offshore wind farm in Scotland, generating since 16 October 2023. Planning permission was granted on 16 May 2017, 55 months after submission. Operator of record: SSE / Seagreen Wind Energy Ltd.

1.07 GW
Capacity
as recorded in REPD
Operational
Status
since 16 October 2023
Wind Offshore
Technology
SSE / Seagreen Wind Energy Ltd
National
Authority
Scotland

Planning and build timeline

Application submitted23 October 2012
Permission granted16 May 2017
55 months after submission
Operational16 October 2023
77 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Seagreen’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

How big is Seagreen?

Seagreen has a recorded installed capacity of 1.07 GW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Seagreen?

REPD records the operator as SSE / Seagreen Wind Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Seagreen approved and built?

The application was submitted on 23 October 2012. Permission was granted on 16 May 2017, 55 months later. The site became operational on 16 October 2023, 77 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2540.