Novarly ParcelRenewable sites

Renewable sitesMorlais Demonstration Zone

Morlais Demonstration Zone

Morlais Demonstration Zone is a 240 MW tidal stream array under construction in Wales. Planning permission was granted on 1 December 2021, 27 months after submission. Operator of record: Menter Mon Morlais.

240 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Tidal Stream
Technology
Menter Mon Morlais
National
Authority
Wales

Planning and build timeline

Application submitted16 September 2019
Permission granted1 December 2021
27 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Morlais Demonstration Zone’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

How big is Morlais Demonstration Zone?

Morlais Demonstration Zone has a recorded installed capacity of 240 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Morlais Demonstration Zone?

REPD records the operator as Menter Mon Morlais. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Morlais Demonstration Zone approved and built?

The application was submitted on 16 September 2019. Permission was granted on 1 December 2021, 27 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6611.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode