Renewable sitesMoray West Offshore Wind Farm Project

Moray West Offshore Wind Farm Project

Moray West Offshore Wind Farm Project is an 882 MW offshore wind farm under construction in Scotland. Planning permission was granted on 14 June 2019, 11 months after submission. Operator of record: EDPR.

882 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Offshore
Technology
EDPR
National
Authority
Scotland

Planning and build timeline

Application submitted5 July 2018
Permission granted14 June 2019
11 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Moray West Offshore Wind Farm Project’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

How big is Moray West Offshore Wind Farm Project?

Moray West Offshore Wind Farm Project has a recorded installed capacity of 882 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Moray West Offshore Wind Farm Project?

REPD records the operator as EDPR. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Moray West Offshore Wind Farm Project approved and built?

The application was submitted on 5 July 2018. Permission was granted on 14 June 2019, 11 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6158.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode