Renewable sites › Moray East
Moray East
Moray East is operational in Scottish Government (S36) with a recorded capacity of 950 MW, and has been generating since 2022-04-01.
Planning and build timeline
| Application submitted | 2012-08-28 |
| Permission granted | 2014-03-19 19 months after submission |
| Operational | 2022-04-01 96 months after consent |
How big is Moray East?
Moray East has a recorded installed capacity of 950 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Moray East?
REPD records the operator as Diamond Green Limited, CTG & Ocean Winds. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Moray East approved and built?
The application was submitted on 2012-08-28. Permission was granted on 2014-03-19, 19 months later. The site became operational on 2022-04-01, 96 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2534.