Novarly ParcelRenewable sites

Renewable sitesMarley Thatch Solar Farm

Marley Thatch Solar Farm

Marley Thatch Solar Farm is an operational 6.3 MW solar farm in South Hams, generating since 31 March 2013. Planning permission was granted on 28 June 2012, 3 months after submission. Operator of record: TGC Renewables.

6.3 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2013
Solar Photovoltaics
Technology
TGC Renewables
South Hams
Authority
England

Planning and build timeline

Application submitted29 March 2012
Permission granted28 June 2012
3 months after submission
Operational31 March 2013
9 months after consent

Screening a site of your own?

RedlineUK · £39

South Hams approves 93% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Marley Thatch Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Hams’s record on solar

South Hams has decided 27 solar farms and approved 93%, taking a median of 3.3 months. See every solar farm decision in South Hams

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
5.21.7 km
Solar Photovoltaics · Operational
6.43.5 km
Solar Photovoltaics · Operational
85.3 km
Solar Photovoltaics · Operational
55.8 km
Solar Photovoltaics · Operational
4.98.4 km
Solar Photovoltaics · Operational
6.59.8 km
Solar Photovoltaics · Operational
1.911.7 km
Solar Photovoltaics · Operational
513.3 km

How big is Marley Thatch Solar Farm?

Marley Thatch Solar Farm has a recorded installed capacity of 6.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Marley Thatch Solar Farm?

REPD records the operator as TGC Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Marley Thatch Solar Farm approved and built?

The application was submitted on 29 March 2012. Permission was granted on 28 June 2012, 3 months later. The site became operational on 31 March 2013, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1467.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode