Novarly ParcelRenewable sites

Renewable sitesLussa

Lussa

Lussa is an operational 2.4 MW hydro scheme in Argyll and Bute, generating since 1 January 1952. REPD does not record the planning grant date. Operator of record: Scottish and Southern Energy (SSE).

2.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1 January 1952
Small Hydro
Technology
Scottish and Southern Energy (SSE)
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submittednot recorded
Permission grantednot recorded
Operational1 January 1952

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Argyll and Bute: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Lussa’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

How big is Lussa?

Lussa has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lussa?

REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lussa approved and built?

REPD does not record a submission date. REPD does not record a grant date. The site became operational on 1 January 1952.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 466.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode