Kincardine Offshore Windfarm is operational in Scotland with a recorded capacity of 49.5 MW, and has been generating since 2021-10-19.

49.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2021-10-19
Wind Offshore
Technology
Grupo Cobra
National
Authority
Scotland

Planning and build timeline

Application submitted2016-06-16
Permission granted2017-03-07
9 months after submission
Operational2021-10-19
55 months after consent

How big is Kincardine Offshore Windfarm?

Kincardine Offshore Windfarm has a recorded installed capacity of 49.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Kincardine Offshore Windfarm?

REPD records the operator as Grupo Cobra. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Kincardine Offshore Windfarm approved and built?

The application was submitted on 2016-06-16. Permission was granted on 2017-03-07, 9 months later. The site became operational on 2021-10-19, 55 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6136.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council