Hywind Scotland Pilot Park (Hywind 2) Demonstrator
Hywind Scotland Pilot Park (Hywind 2) Demonstrator is an operational 30 MW offshore wind farm in Scotland, generating since 27 October 2017. Planning permission was granted on 30 October 2015, 7 months after submission. Operator of record: Statoil.
Planning and build timeline
| Application submitted | 27 March 2015 |
| Permission granted | 30 October 2015 7 months after submission |
| Operational | 27 October 2017 24 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Hywind Scotland Pilot Park (Hywind 2) Demonstrator’s recorded coordinate — swap in your own postcode or coordinates.
How big is Hywind Scotland Pilot Park (Hywind 2) Demonstrator?
Hywind Scotland Pilot Park (Hywind 2) Demonstrator has a recorded installed capacity of 30 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hywind Scotland Pilot Park (Hywind 2) Demonstrator?
REPD records the operator as Statoil. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hywind Scotland Pilot Park (Hywind 2) Demonstrator approved and built?
The application was submitted on 27 March 2015. Permission was granted on 30 October 2015, 7 months later. The site became operational on 27 October 2017, 24 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2479.